EcoDataCenter is building a new AI data center campus in Borlänge, Sweden, with 250MW of initial power access. The company says that figure could later grow to 600MW.
By power access, the Borlänge site is roughly three times the size of the company’s Falun campus. Falun has 80MW of secured supply for its full expansion.
Both numbers describe access to electricity, not actual use. Real consumption will depend on the equipment installed and how it runs.
Mistral Joins the Borlänge Project
The company broke ground in September 2025 at the former Kvarnsveden paper mill in Borlänge. Its schedule puts completion of the first data center in early 2027.
In February 2026, French AI company Mistral and EcoDataCenter announced a €1.2 billion investment commitment through the project. The opening is planned for 2027.
Under the deal, EcoDataCenter would design, build and operate the infrastructure. Mistral would deploy the computing capacity. The announcement did not say how much of the campus’s power Mistral would use.
What Falun Shows So Far
At Falun, server heat goes to a neighboring energy plant, which uses it to dry wood pellets. The buildings use panels made from layers of timber.
According to EcoDataCenter’s 2025 sustainability report, Falun’s purchased electricity came from 75% hydropower and 25% wind. The campus consumed 112.5 million kWh during the year.
About 531,000kWh of that energy was reused outside the campus. That works out to roughly 0.5% of total consumption, with the heat going to pellet production.
At the end of 2025, the company connected a liquid-cooled AI cluster to its heat recovery system. It forecast more hours of heat recovery during 2026.
The company has also described limits to expanding its existing recovery system. More operating hours could raise the amount of heat reused, but only if recipients can take it.
Any similar heat benefit at Borlänge would depend on local demand for the heat. It would also depend on the energy needed to move it there.
In 2022, EcoDataCenter said it was investing about 50 million Swedish kronor in grid work with Ellevio and Falu Energi & Vatten. The company stated that reinforcement between Borlänge and Falun would improve grid stability and add municipal electricity capacity.
The company classified 58% of its 2025 capital spending as local. That figure covers the whole company, not a single site.
For residents of Falun and Borlänge, a fuller picture of lasting benefits would include permanent jobs and apprenticeships. It would also include contracts for local suppliers that extend beyond construction.
Around Falun, hydro, solar and wind output sometimes exceeds what the grid needs, the Guardian reported on November 12. A large data center can absorb that surplus when its demand lines up with extra generation.
Measuring that benefit would require hourly figures. Those figures would show how much power would otherwise go unused.